WPRZ 88.1 FM Is Under Construction!
May 10, 2010
Today, the transmitter arrived!! Tomorrow the electricians will begin the installation of the electric. This may take some time as permits have to come from Culpeper County for the electric in the building and then the ditch for the electric cable will be dug.
May 6 - 7, 2010
On Thursday and Friday, the antennas and cable were installed. This was a major accomplishment! It took two guys most of Thursday to get the antennas up and installed in the proper positions and then on Friday, the cable was installed up the tower to the antennas.
May 5, 2010
Today the antenna and the cable arrived. The day was spent assembling the antenna and making sure all the proper pieces were in place. A surveyor was also present to make sure the antennas were pointing in the right direction.
May 4, 2010
Today was a huge day for WPRZ FM! The actual physical construction of the station began!! Today Smith-Midland brought the concrete building up to the tower site in 6 pieces on a truck that had to be helped up the steep road by a bulldozer! Why? The concrete building weighed 25,000 pounds! The building had to be constructed of concrete because of ice that may fall from the 300 foot tower in the winter months. Anything other than concrete wouldn’t hold up under those circumstances. Each of the pieces was carefully lifted off the truck by a big crane and carefully placed into position. It was quite a sight to see. Mark and his crew did a fantastic job!!!